Short Review of PBI report: Financing of Large-scale Infrastructure, case Nordic Connector (FLINC)
Financing of Large-scale Infrastructure, case Nordic Connector (FLINC)
Guide:
Square bullets are from the PBI report, unfilled circles are my comments
PBI’s
financing perspectives for the Nordic Connector:
§ “The
Nordic Connector should not be viewed as a single infrastructure project,
but rather as a program investment consisting of several interrelated
subprojects.”
o
Nordic Connector (NC) must be viewed as a
project on its own right. Expanding it to include many subprojects
overcomplicates and causes delays. Subprojects can be included later.
§ “Large-scale
transport infrastructure is seldom fully self-financing through user charges.
The Nordic Connector is no exception to this. Instead, investments of this
scale are typically justified by broader socio-economic and strategic benefits.”
o No
“typical” case is shown. No benefit without willingness to pay! User charge is
important.
§ “Financial
modelling demonstrates that financial feasibility is conditional rather than
fixed. Under favourable assumptions the
project can achieve financial sustainability. The analysis shows that no single
factor is sufficient on its own; a combination of measures is required”
o
No such analysis was made. NPV for the
favorable and optimistic scenarios is positive (and at a low traffic estimate!)
and road tolls pay the loans off in 30 years!
§ “A
hybrid model based on a publicly owned Special Purpose Vehicle (SPV) is
identified as the most viable financing structure. In this model, Finland and
Sweden Jointly establish and own SPV … Public sector involvement, including
state guarantees …to enable long-term debt financing.”
o SPV,
type Öresund or E-18, are possible with state loan guarantees. EU grants are
likely.
§ “Public
co-financing for the Nordic Connector will be critical.
EU instruments, particularly the Connecting Europe Facility (CEF) and Military
Mobility, are the most relevant of 10–30% of total.”
o
CEF and Military Mobility contribution likely
range is 30-50%.
§ “A central
conclusion is of distinguishing between bankability and societal value. The fixed
link is not bankable on user charges; it may generate substantial Wider
Economic Impacts (WEI).“
o
NC road may be fully bankable on user charges
plus CEF grant. Non-monetized WEI are important for public acceptance.
§ “The
key question is therefore not whether the project can pay for itself, but
whether its wider economic and strategic benefits are sufficient to justify the
required public investment.
o Public acceptance of NC should be assessed and developed using a professional
application of Policy Delphi (such as RD Aluekehitys Delfoi) or complementary
methods.
Recommended next steps from a financing perspective for the Nordic Connector:
§ “Securing
TEN-T status for the Nordic Connector and key nodes along its route.
§ Clarifying
eligibility potential for EU funding through early engagement with EU
institutions.
§ Advancing
bilateral agreements between Finland and Sweden on governance and SPV
structure.”
“Nordic
Connector should be considered as a logistic and redundancy infrastructure
investment.”
o
Foremost NC should be considered an economic
investment with widespread public acceptance. Risk Intelligence Systems ranks
E12 as the most important east-west project.
Background,
Aim, Scope of PBI Study
PBI
report’s traffic and cost forecasts use FTIA study on Vasa-Umeå fixed link. The
traffic forecast is based on many faulty assumptions. Options 4 – 6 (Fig. 2)
should be rejected outright due to cost and not being financeable. Rail options
are not realistic from demand, cost, and WEI perspectives.
The key questions:
§ “Is Nordic
Connector bankable as an investment? If yes, under what circumstances?”
o
Yes, provided that the governments carry out
the recommended next steps
o PBI’s financing structures are conceptual. In Sweden a legal framework for tolls and for a private infrastructure investment exists. In Finland, a similar legal framework does not, and should be updated already by the current government.
o PBI
claims: “The forecasting horizon for this type of extensive
infrastructure investments are typically long (50 years).” Reference
examples to such projects should be provided. Although
many transport facilities serve over 50 years they need reinvestments
after 25-30, often sooner. To my knowledge no transport facility has
been justified or financed with a 50 year horizon.
§ “Can Wider
Economic Impacts (WEI) generated by the Nordic Connector … support Nordic
Connector becoming bankable?”
o
It is likely that WEI will exist. They are
important to inform about the project to develop public acceptance and widespread
support for it. But WEI should not be included in the economic evaluation in
Nordic Connector decision, only to gauge its public acceptance.
The
principal questions concern organization structure and financing.
The CapEx
Risk Reserve in Table 5 is too large. Normally
“CapEx Risk Reserves” are part of the bidder information in procurement to
evaluate bidder capability. The cost estimate contingency is often 10-15% and
included in the bidder’s BAFO. The risk provision of 70% is too large.
The Annual
OpEx of 10 MEUR is also large and road construction time of 7-10 years is high.
The land portions are part of the National Network and not an SPV
responsibility. O&M maybe for 5 years.
Risk
Assessment and Bankability
Most of
these risks cited are considered in the permitting or the procurement processes.
Three risks are left unsaid: the contractor risk of not being able to complete
the project; the risk of not having NC as fixed link; and mobilization risks.
Mitigation measures and liquidated damages should be identified for the first;
the loss of benefits for the second if the Gulf of Finland and the Baltic Sea are
closed; and the need for air transports in the third (Kauhava airport becomes
critical – not the railways, nor Narvik port).
PBI’s Summary of Recommendation
“The
decision to proceed should therefore not be based solely on financial
feasibility, but on a comprehensive assessment of long-term economic, strategic
and societal value.”
o In many
cases, traffic estimates have been underestimated. Financial feasibility with
road tolls is probable. An example of traffic forecasts when a fixed connection
replaced a ferry:
ü Welde, M
and E. Tveter, J. Odeck (2018) “The Accuracy of Traffic Forecasts or Fixed Link
Projects: An Empirical Study of Norwegian Bridges and Tunnels.” Paper at
European Transport Conference. [Note: There was no diversion possibility
from alternative routes].
Ø Traffic growth was observed. Three years after opening
the average growth was 22% and after 5 years after opening 37%. Increase in
traffic from the last full year of ferry traffic to the first full year of the
fixed link up to 2015 was 116% (n=38, various opening years since 1970). The
average annual growth was 6% (n=23).
§ “The
financial analysis shows that the Nordic Connector is not financially
self-sustaining on user revenues alone under conservative assumptions.
Under more optimistic scenarios, bankability and financial feasibility NC becomes
viable.”
o
Analyses show that NC is self-sustaining
under reasonable assumptions, table 5. PBI need to show on what range of
traffic, tolls, and construction costs NC would be self-sustaining.
§ “The
results from the ongoing analysis of Wider Economic Impacts (WEI) in Work
Package 2
play a central role in the overall assessment of Nordic Connector.”
o
WEI analyses cannot be falsified (even in the
future) and should not be accepted in BCA analyses. Should they occur, they
would be a social benefit not only to those making the WEI investments. If
included in BCA, and WEI fail to occur, they would be a cost to the taxpayers.
o Ex-ante studies, such as Delphi
studies (e.g. by RD Aluekehitys), should inform the public and gauge the
project outcomes on user and stakeholder groups across different geographical
areas. Stakeholder groups could be: (1) transport and trade, industry, tourism
and other businesses; (2) research and education; (3) public administration;
and (4) civil society.
o
Ex-post WEI studies are also important
for big projects. They would inform about reliability and usefulness of ex-ante
WEI studies. Ex-post studies would improve travel demand forecast and cost
estimation methods, and application of both. revised
Here is the NC benefit-cost analysis with reworked
traffic forecast and tolls.
(Click for larger image)